课 Progress
0% Complete

Gantt charts

What is a Gantt (cascade) chart?

  • A Gantt chart – also known as a cascade chart – is a graphical display of the activities making up a project

    • a Gantt chart shows

      • the critical activities

      • the total float for non-critical activities

      • the minimum project duration

  • Gantt charts can be used in resource levelling and scheduling problems when the number of workers for each activity is known

    • in the first instance, a Gantt chart assumes one worker per activity

How do I draw a Gantt (cascade) chart?

  • (Usually) a horizontal axis is drawn for time and this appears at the top of the Gantt chart 

  • Activities are then drawn as a series of bars (rectangles) underneath

    • each activity is assumed to commence at its earliest event time

      • i.e. at the early event time of its start node 

    • each activity is assumed to occur in a single block of time

      • i.e. no breaks!

      • e.g. an activity of duration 5 and early event time 4 would be drawn as a bar starting at 4 and ending at 9

    • Critical activities are all drawn in the same horizontal line

      • these have a total float of zero so are drawn back-to-back

    • Non-critical activities

      • are drawn one per line

      • have their total float indicated by a bar drawn with a dotted line

      • e.g. an activity of duration 4, early event time 7 and total float 3 would be drawn as a (solid) bar starting at 4 and ending at 11, with a dotted bar starting at 11 and ending at 14

    • Bars are labelled with their activity name and duration

      • floats are not labelled

  • For the activity network below

    • the critical activities are highlighted and are A, C, G and I

      • (the critical path is A-C-G-I)

    • the minimum project duration is 23 (days)

ElwVRYwN_gantt-network
  • The Gantt chart for the project would be constructed with

    • a horizontal axis running from 0 to (at least) 23

      • (0 to 25 keeps things nice!)

    • critical activities A, C, G and I drawn back-to-back on a single line underneath

    • activities B, D, E, F, H and J are each drawn on a separate line

      • e.g. activity D will be drawn as a solid bar from 4 to 7 with a dotted bar from 7 to 12

2oXg3ddT_gantt-chart

Examiner Tips and Tricks

  • An exam question is likely to provide a grid and the axes for you to draw a Gantt chart on

  • For a non-critical activity the dotted float bar can be seen as room that the activity bar can slide back and forth along to vary it’s start and end time

Responses

您的邮箱地址不会被公开。 必填项已用 * 标注