Back to 课程

Business_A-level_Edexcel

0% Complete
0/0 Steps
  1. 1-marketing-and-people

    1-1-meeting-customer-needs
    3 主题
  2. 1-2-market
    5 主题
  3. 1-3-marketing-mix-and-strategy
    5 主题
  4. 1-4-managing-people
    5 主题
  5. 1-5-entrepreneurs-and-leaders
    6 主题
  6. 2-managing-business-activities
    2-1-raising-finance
    4 主题
  7. 2-2-financial-planning
    4 主题
  8. 2-3-managing-finance
    3 主题
  9. 2-4-resource-management
    4 主题
  10. 2-5-external-influences
    3 主题
  11. 3-business-decisions-and-strategy
    3-1-business-objectives-and-strategy
    4 主题
  12. 3-2-business-growth
    4 主题
  13. 3-3-decision-making-techniques
    4 主题
  14. 3-4-influences-on-business-decisions
    4 主题
  15. 3-5-assessing-competitiveness
    3 主题
  16. 3-6-managing-change
    3 主题
  17. 4-global-business
    4-1-globalisation
    5 主题
  18. 4-2-global-markets-and-business-expansion
    5 主题
  19. 4-3-global-marketing
    3 主题
  20. 4-4-global-industries-and-multinational-corporations
    3 主题
  21. 5-exam-technique
    5-1-the-exam-papers
    4 主题
  22. 5-2-business-studies-skills
    1 主题
  23. 5-3-structuring-your-responses
    5 主题
  24. 6-pre-release-preparation
    2025-pre-release-music-industry
    9 主题
课 Progress
0% Complete

The nature and purpose of critical path analysis

  • Critical path analysis is a project management tool that uses network analysis to plan complex and time-sensitive projects 

  • Critical path analysis involves the construction of a visual model of the project that includes key elements:

    • A list of all activities required to complete the project

    • The time (duration) that each activity will take to complete

    • How each project activity depends on others

  • Critical path analysis shows:

    • The order in which activities must be completed

    • The longest path of project activities to the completion of the project

    • The earliest and latest that each project activity can start and finish without delaying completion of the project as a whole

    • Activities within a project that can be carried out simultaneously

    • The critical project activities that, if delayed, will cause the project as a whole to overrun

    • Those project activities where some delay is acceptable without delaying the project as a whole

    • The shortest time possible to complete the project

  • It allows managers to identify the relationships between the activities involved and to work out the most efficient way of completing the project

    • Resources such as raw materials and components can be ordered or hired at precisely the right time they are needed

    • Working capital may be managed efficiently

    • Where delays occur, managers can identify the implications for the project’s completion and redirect resources if required 

Drawing critical path analysis diagrams

Components of network analysis diagrams

Element

Description

Node

  • A node is a circle that represents a point in time where an activity is started or finished

  • The node is split into three sections

  • The left half of the circle is the activity number 

  • The top right section shows the earliest start time (EST) that an activity can begin based on the completion of the previous activity

  • The bottom right section shows the latest finish time (LFT) by which the previous activity must be completed

Activities

  • An activity is a process or task within a project that takes time

  • Activities are shown on the network diagram as a line that links nodes 

  • A description of the activity or a letter representing the activity is usually shown above the line

Duration

  • The duration is the length of time it takes to complete an activity

  • The duration is shown as a number of time units, such as hours or days, below the activity line

Example network diagram

Flowchart diagram illustrating a project schedule with nodes, activities, durations, earliest start time (EST), and latest finish time (LFT).
A simple network diagram showing key elements: node, activity and duration
  • A network diagram must always start and end at a single node

  • Lines must not cross and must only be assigned to activities

Critical path calculations

Earliest start times

Network diagram with circles A to H connected by lines. Each circle contains two numbers; lines are labelled with single-digit numbers.
An example of a simple network diagram showing earliest start times
  • Working forwards from Node 1, it is possible to calculate the earliest start time (EST) for each activity by adding the duration of each task

  • The EST for each activity is placed in the top right of each node

    • Node 1 is the starting point of the project and where both Activity A and Activity B begin

    • Activity A and Activity B are independent processes

    • Activity A has a duration of two days, and its EST is zero days

    • Activity B has a duration of three days, and its EST is also zero days

    • Activity C and Activity D both begin at Node 2 and are dependent upon the completion of Activity A but are independent from each other

      • Activity C has a duration of three days, and its EST is two days 

      • Activity D has a duration of five days, and its EST is also two days

    • Activity E begins at Node 3

      • Activity E has a duration of four days, and its EST is three days

    • Activity F begins at Node 4

      • Activity F has a duration of two days, and its EST is five days

    • Activity G begins at Node 5

      • Activity G has a duration of one day, and its EST is seven days

    • Activity H begins at Node 6

      • Activity H has a duration of three days, and its EST is seven days

    • Node 7 is the endpoint of the project

Latest finish times

Network graph with nodes labelled A to H and numbered 0 to 7. Lines show connections and weights between nodes. Nodes have multiple values inside circles.
An example of a simple network diagram showing ESTs and LFTs
  • Working backwards from Node 7, it is now possible to calculate the latest finish time (LFT) for each activity by subtracting the duration of each task

  • The LFT for each activity is placed in the bottom right of each node

    • Node 7 is the endpoint of the project, which has an LFT of ten days

    • Activity H has a duration of three days

      • The LFT in Node 6 is seven days (10 days − 3 days)

    • Activity G has a duration of one day

      • The LFT in Node 5 is nine days (10 days − 1 day)

    • Activity F has a duration of two days

      • The LFT in Node 4 is eight days (10 days − 2 days)

    • Activity E has a duration of four days

      • The LFT in Node 3 is three days (7 days − 4 days)

    • Activity D has a duration of five days

      • The LFT in Node 2 is four days (9 days − 5 days)

    • Activity C has a duration of three days

      • The LFT in Node 3 is four days because Activity D is the more time-critical of the two activities that are dependent upon the completion of Activity A, so its LFT is recorded

    • Activity B has a duration of three days

      • The LFT in Node 1 is zero days (3 days − 3 days)

    • Activity A has a duration of two days

      • The LFT in Node 1 is zero days because Activity B is the more time-critical of the two starting activities, so its LFT is recorded

  • The LFT in Node 1 is always zero

Identifying the critical path

  • The critical path highlights those activities that determine the length of the whole project

    • If any of these critical activities are delayed, the project as a whole will be delayed

    • The critical path follows the nodes where the EST and LFT are equal

      • In the diagram below, Nodes 1, 3, 6 and 7 have equal ESTs and LFTs

      • Activities that determine these nodes are B, E and H

      • These activities are marked with two short lines

      • The critical path is therefore BEH

Network flow diagram with nodes A to H, each with capacity and flow. Arcs include values like A-2, C-4, and B-3, with paths marked in red and blue lines. The critical path is red.
An example of a simple network diagram showing the critical path, BEH

Identifying and calculating float time

  • Float time exists where there is a difference between the EST and the LFT

  • Where float time is identified, managers may:

    • Transfer resources, such as staff or machinery, to more critical activities

    • Allow extra time to complete tasks to improve quality or allow for creativity

<img alt=”Network diagram showing nodes with calculations and notes on differences at nodes 4, 5, and 6. Includes paths A-H and float time information.” data-nimg=”1″ decoding=”async” height=”919″ loading=”lazy” sizes=”(max-width: 320px) 320w, (max-width: 640px) 640w, (max-width: 960px) 960w, (max-width: 1280px) 1280w, 1920w” src=”https://cdn.savemyexams.com/cdn-cgi/image/f=auto,width=3840/https://cdn.savemyexams.com/uploads/2023/05/3-3-4-identifying-and-calculating-float-time.png” srcset=”https://cdn.savemyexams.com/cdn-cgi/image/f=auto,width=16/https://cdn.savemyexams.com/uploads/2023/05/3-3-4-identifying-and-calculating-float-time.png 16w, https://cdn.savemyexams.com/cdn-cgi/image/f=auto,width=32/https://cdn.savemyexams.com/uploads/2023/05/3-3-4-identifying-and-calculating-float-time.png 32w, https://cdn.savemyexams.com/cdn-cgi/image/f=auto,width=48/https://cdn.savemyexams.com/uploads/2023/05/3-3-4-identifying-and-calculating-float-time.png 48w, https://cdn.savemyexams.com/cdn-cgi/image/f=auto,width=64/https://cdn.savemyexams.com/uploads/2023/05/3-3-4-identifying-and-calcul

Responses

您的邮箱地址不会被公开。 必填项已用 * 标注