Gantt charts
What is a Gantt (cascade) chart?
-
A Gantt chart – also known as a cascade chart – is a graphical display of the activities making up a project
-
a Gantt chart shows
-
the critical activities
-
the total float for non-critical activities
-
the minimum project duration
-
-
-
Gantt charts can be used in resource levelling and scheduling problems when the number of workers for each activity is known
-
in the first instance, a Gantt chart assumes one worker per activity
-
How do I draw a Gantt (cascade) chart?
-
(Usually) a horizontal axis is drawn for time and this appears at the top of the Gantt chart
-
Activities are then drawn as a series of bars (rectangles) underneath
-
each activity is assumed to commence at its earliest event time
-
i.e. at the early event time of its start node
-
-
each activity is assumed to occur in a single block of time
-
i.e. no breaks!
-
e.g. an activity of duration 5 and early event time 4 would be drawn as a bar starting at 4 and ending at 9
-
-
Critical activities are all drawn in the same horizontal line
-
these have a total float of zero so are drawn back-to-back
-
-
Non-critical activities
-
are drawn one per line
-
have their total float indicated by a bar drawn with a dotted line
-
e.g. an activity of duration 4, early event time 7 and total float 3 would be drawn as a (solid) bar starting at 4 and ending at 11, with a dotted bar starting at 11 and ending at 14
-
-
Bars are labelled with their activity name and duration
-
floats are not labelled
-
-
-
For the activity network below
-
the critical activities are highlighted and are A, C, G and I
-
(the critical path is A-C-G-I)
-
-
the minimum project duration is 23 (days)
-

-
The Gantt chart for the project would be constructed with
-
a horizontal axis running from 0 to (at least) 23
-
(0 to 25 keeps things nice!)
-
-
critical activities A, C, G and I drawn back-to-back on a single line underneath
-
activities B, D, E, F, H and J are each drawn on a separate line
-
e.g. activity D will be drawn as a solid bar from 4 to 7 with a dotted bar from 7 to 12
-
-

Examiner Tips and Tricks
-
An exam question is likely to provide a grid and the axes for you to draw a Gantt chart on
-
For a non-critical activity the dotted float bar can be seen as room that the activity bar can slide back and forth along to vary it’s start and end time